Holcomb & WIlson Sewer Upsizing project

Chip Seal Overview Map

 

Holcomb & Wilson sewer upsizing project

Project Update: July 9, 2025 

 As part of the City of Port Townsend’s efforts to improve the capacity and reliability of our sewer system, geotechnical drilling will be conducted along Holcomb Street and Sims Way to support the future Holcomb & Wilson Sewer Upsizing Project. 

Project Schedule 

  • Date & Time: Wednesday, July 16, 2025, approximately 9:00 AM to 3:00 PM
  • Location: Roadway right-of-way near Holcomb Street and Sims Way
  • Activity: Soil borings using a truck- or track-mounted drill rig and support vehicle
  • Impacts: No road closures are expected. Temporary parking restrictions and minor traffic disruptions may occur.
  • Restoration: Drilled pavement will be restored with material matching the existing surface (asphalt or concrete)  

 

Project contact:
Mike Connelly, P.E., Project Manager
mconnelly@cityofpt.us