6) BUILDING: How do I figure the project valuation?

Enter the project valuation in the appropriate line on the Permit Application Form.

The permit valuation shall include the total value of the work for which a permit is being issued. This includes materials and labor for the permanent structure and mechanical, electrical, plumbing and gas, fire sprinkler and elevator systems and equipment. Permanent systems such as audiovisual, lighting and HVAC controls are included in the total as are expenses directly related to construction such as equipment rental and contractor fees.  Costs such as architectural and engineering design fees, landscaping and planting, tap fees, development mitigation fees, trash removal, and cleaning are not included.